Why are Hungarians afraid to let passengers on the Falcon?The Falcon would fly, but without passengers for now: Hungary is testing the Belgrade-Budapest high-speed railway
A lot can happen to a railway line in seven months, especially when a change of government occurs at one end and a tragedy at the other threatens safety. Freight trains have been running on the Budapest-Belgrade railway line since February, but passenger traffic is still waiting. The Hungarian side has now put the track and the safety equipment to a greater test than ever: the trains were already running according to schedule for a while, but passengers were not allowed on board.
The most comprehensive test to date took place on the Hungarian section of the Budapest-Belgrade railway line: the Sólyom trains were already running as if passenger traffic had started - only under cover of night, and there were no passengers on board.
The Serbian Sólyom is already on its way to Budapest, freight trains have been running since February, but passengers have only reached the platform. According to Vreme, the Hungarian authorities are subjecting the Budapest-Belgrade railway line to stricter tests than ever before, and seven months after the originally planned start of passenger traffic, they are refusing to let passengers on the trains.
The new Hungarian government, which took office in the spring, apparently does not intend to accept the claims of either the Chinese contractors, the previous Hungarian leadership, or even the Serbian side: first, everything should work as it should according to the papers.
Fly, Falcon – just don't let anyone sit on you!
This is how the current attitude of the Hungarian authorities towards the high-speed railway between Budapest and Belgrade could be summed up. The trains can run, the systems can be loaded, the timetable can be changed – as long as there are no passengers on the trains.
According to Vreme, the line is currently undergoing perhaps the most rigorous test in its history, as far as we know: the evaluation could take days.
The distrust intensified after the change of government in Hungary in the spring, when the new leadership began to more closely examine the less transparent Chinese contracts concluded during the Orbán government and the cooperation with the Serbian side.
According to the original plans, passenger traffic between Budapest and Belgrade was supposed to start in March. It is October and Budapest is still testing the safety systems.
Vreme also links Hungarian caution to the collapse of the Novi Sad railway station canopy. The wave of political and social protests that followed the tragedy eventually led to elections in Serbia, so according to the newspaper, it is understandable that the Hungarian side is trying to rule out any similar scenario.
They pretended at night that everything was working.
Minister of Transport and Investment Dávid Vitézy recently reported on social media that the "most comprehensive" test of the Budapest-Belgrade railway to date has been completed.
The test was carried out at night. However, the trains ran for hours exactly as if regular passenger traffic had already started: they followed the planned daily schedule, and in accordance with the order developed for the highest traffic load.
There was only one significant difference: there were no passengers on the trains.
According to Vitézy, the train control system, which is a key element of the railway line's handover, worked well, and without which safety cannot be guaranteed at the operating speed of 160 kilometers per hour.
Previously, problems arose with this very system.

Vitézy on the train, which can travel at a maximum speed of 160 km/h (Source: Facebook , Dávid Vitézy)
The Hungarian minister emphasized again: the basic principle remains unchanged, safety comes first. Passenger transport can only start if it has been clearly established that nothing endangers passengers.
According to Vitézy, this is precisely why the rigorous tests have been underway since the summer, and why the full-scale simulation this weekend was an important step. Once the official evaluation is complete, the results will be made public.
The minister added a sentence that is hardly independent of the practice of the previous era: passengers must be informed in a timely manner, not hidden from them, which, according to "leftist opinion", could be interpreted as open criticism of either the previous Hungarian or the current Serbian government.
They left fifteen days for safety – it turned into seven months
The "train" scene was quite different in February. Vreme reminded us that freight transport on the high-speed railway between Belgrade and Budapest started on February 27, a fact that former Serbian President Aleksandar Vučić proudly boasted about.
Together with the then Hungarian Minister of Construction and Transport, János Lázár, they also announced that passenger traffic would soon begin.
The plan was to wait until March 15. The intervening fifteen days were intended to complete all technical and safety checks.
How the 15 days turned into seven months is not entirely clear, but it is clear that following the April announcement, elections were held in Hungary, in which Viktor Orbán , a longtime ally of the progressive regime in Serbia, lost power.
After the change of government in Hungary, Serbian Minister of Construction, Transport and Infrastructure Aleksandra Sofronijević said on RTS that Serbia is ready to start passenger traffic to Budapest, and the date of the railway opening depends solely on the Hungarian side.
So, the responsibility in Serbia has once again been shifted to Hungary, not for the first time, and probably not for the last time, but we are the only ones who note this, not out of mere malice, but rather from experience.
The Serbian minister spoke of a “technical problem.” Sofronijević also acknowledged that the Hungarians had found a bug that affected traffic safety.
"This means that the Hungarian side - primarily MÁV - i.e. the national railway company and operator, is conducting inspection and safety inspections on the so-called ETCS system, as an error has occurred and been identified that endangers traffic safety at speeds of 160 kilometers per hour," said the Serbian minister.
Let us note here that according to Vitézy, it can already be said: the test basically went well, and the train control system, which can be considered a critical issue for the handover, guaranteed complete safety even at a maximum speed of 160 km/h.
However, he said that the operation of the passenger information systems was not satisfactory, and therefore the contractor must improve them.
ETCS has spread its wings to the Falcon
In this context, the Serbian Sofronijević noted that Soko railcars had previously visited Hungary and had obtained the necessary type approval and certificate.
However, this does not automatically mean that they can be put into regular service.
To do this, all safety systems must function properly, the necessary safety certificates must be obtained, and then the individual permit for Sólyom fittings must be obtained.
However, the months passed, and the passenger trains did not depart, Vreme stated bitterly, but still factually.
The new Hungarian government wants to see Chinese contracts too
Dávid Vitézy spoke much harsher in the Hungarian parliament in June. He said that one often hears the claim that the Chinese “didn’t even know what they were doing.”
According to the minister, it is also necessary to examine whether Hungary and Serbia have really managed to steer the development of the Budapest-Belgrade railway line in the right direction.
Vitézy indicated that permission must be sought from the Chinese authorities to make public the contracts, their amendments and all related documents, including data on costs and invoices, Vreme quoted him as saying.
The minister said at the time that the situation was still not completely resolved. Although the completion of the railway construction had been delayed due to certain problems, several technical and safety issues remained open.
He particularly highlighted the insurance and traffic management systems, which were not yet fully operational.
Vitézy also made it clear that the system cannot be permanently put into operation – nor fully paid for – until it has been proven that it meets all required security requirements.
A two-hundred-meter railway was built in
However, there is another oddity about the Budapest-Belgrade railway. According to Vitézy, he does not want to protect anyone, but the contract clearly shows that certain technical solutions were already known in advance.
The track was indeed designed for speeds of 200 kilometers per hour, and an almost completely new track was built to accommodate this.
However, a number of level crossings remain. The Hungarian minister called this a serious shortcoming, which in practice means that the planned speed of the railway cannot be used everywhere.
In other words: they built a railway designed for a speed of 200 kilometers per hour, on which in some sections the speed must be limited to 160 kilometers per hour precisely because of unresolved level crossings.
The Falcon could now fly towards Budapest. However, the Hungarians would like to see if it flies safely first – and only then would they put passengers on it.